Work Methodology
Construction Procedure
- Identify and mark test location.
- Measure path length of test location.
- Apply grease onto the concrete surface using scraper.
- Calibrate the Pundit tester with calibration rod to 20.8 µs.
- Start UPV test with putting transmitter onto the greased concrete surface and receiver onto the opposite side.
- Record the transit time as displayed at the LCD of Pundit tester.
- Repeat step 4 three (3) times to get another three (3) reading.
- Pulse velocity was calculated by path length divided by average transit time thru the structure.
- Contour graph shall be plotted using pulse velocity at each location on gridline.
- Result analysis based on guideline from “Non-destructive Testing of Concrete” by Singapore Concrete Institute, 1995.